Happy New year!
Despite the downtime of the holidays, our builders managed to squeeze in some much needed time on the trails in late December and early January. Work was done on Cambodia, Cabin Trail, and More. Keep scrolling to see what they got up to!
To see what our paid Trail Crew is up to, check out the Crew update here: Trail Crew Update
Cambodia
Volunteers: Blaise Ratcliffe & Crew
1) Rock-armored and dirt-filled run out of steep rock slab
2) Cut in the new ‘ride-around’ line.
3) Rock-armored and dirt-filled entrance of new ride around.
4) Decommissioned old ‘ride-around’ line.
Corkscrew
TAP Sponsor: CRSP CPA
CHMC zone: Berm rework, grade reversals added/rebuilt, drainage dug
Metro: prep for multiple cedar projects – milling and bucking slabs from a recently fallen cedar (approved by Metro via email)
Bottletop, Ridgerunner, Bridlepath & High School Trail
Vulunteers: Isabelle Deguise & Cheryl Moore
Clearing trail of debris and downed trees following snow storm
Cabin Trail
TAP Sponsor: Anthem Properties
233 hours of volunteer work were completed on the main trail, including realignments.
162 hours of volunteer work were completed on the new entrance connector
All work following IMBA Canada Prescription
Mystery Creek falls crossing: the entry to the crossing was washed out due to the waterfall flowing onto the trail during a large storm. Washed out portion was built back up using rock fill with rock hardening to the trail tread to reduce damage from any future similar incidents
After completion of the first of the prescribed realignments in 2021, in 2022, the sub-standard TTF ladder bridges were removed and dismantled. Three old discarded ladder bridges were recovered from beside the trail and fully dismantled. In both cases, nails were all removed from the forest and taken for metal recycling
Substandard TTF ladder bridge replaced. Old TTF had too much slat overhang, under sized stringers, and oversized wide spacing. Down ramp on old growth log stabilized with additional timber and two pieces of rock added as foot holds for foot traffic. Organic dirt on exit dug out and replaced with mineral dirt.
First steep corner at head of trail rebuilt with rock armouring protecting roots and providing predictable surface for bikes. Flat sections incorporated to assist foot traffic.
Work was started on 2nd realignment to move trail from narrow, rooty alignment to higher alignment with TTF incorporating bedrock/armoured section for added interest. Work was ceased in this area due to a hazard tree. Work recommenced late in the year until snow stopped progress.
Old, rotten, broken woodwork removed from trail bed and new drain formed
Work was started on a new entrance connector, beginning a short distance from CBC exit, and finishing at the first/upper crossing of Mystery Creek (connector will utilize new bridge to be constructed in August 2023)
Work will continue in 2023 on both the realignments of the main trail, and the new entrance connector – once the snow clears
Meat Sweats
Volunteers: Mark Alderton and crew
Drainage and tread refresh
Latest News
Member Spotlight: Jeannine Avelino
Meet Jeannine Avelino one of our (Runner/Hiker) Members. In your own words, what does being a member of the NSMBA mean to you? It's definitely a give and take relationship so being an NSMBA member allows me to support the backyard in which we spend most of our...
Builder Spotlight: Brent Hillier
Meet Brent one of our Fromme Trail Builders. Trail builders are the backbone of the NSMBA, completing work on the trails week after week, in all conditions. Meet Brent Hillier NSMBA Trail Builder, Outdoor Educator and Consultant, Avalanche Practitioner, Hiking Guide,...
Director Spotlight: Ella Walmsley
Meet Ella one of our Board of Directors. Tell us a little about you? I value being immersed in the world around me, learning about the forest or environment close by or sitting on a couch being surrounded by good friends and conversations. I lived in New Zealand until...